Software for factories that brings maintenance work orders, alarms, SCADA dashboards and machine data into one place.

goConnecto helps maintenance teams react faster to failures and understand machine status with less guesswork. It combines plant structure, requests, work orders, documentation, alarms, live signals and SCADA-style dashboards in one system.

CMMS and machine monitoring for maintenance teams

Maintenance CMMSMachine monitoring and alarmsSCADA dashboards
goConnecto - CMMS and machine monitoring for maintenance teams

Executive Overview

goConnecto helps maintenance teams react faster to failures and understand machine status with less guesswork. It combines plant structure, requests, work orders, documentation, alarms, live signals and SCADA-style dashboards in one system.

Client

goConnecto

Engagement

Product engineering, Industrial IoT, UX and marketing website

Scope

9 · technologies

What This Project Proves

01

Maintenance CMMS

02

Machine monitoring and alarms

03

SCADA dashboards

04

Machine structure and asset management

Business Context

Business Need

Maintenance teams often work across spreadsheets, chat, paper documentation and separate machine panels. Alarms get lost, work history is fragmented and decisions are made without full operational context.

Why It Matters

The result is one place for requests, work orders, documentation, alarms and operational data. goConnecto can start as a maintenance system and grow into connected machine monitoring and SCADA dashboards.

Quick Facts

24/7

machine state and alarm visibility

1

shared maintenance timeline

∞

machine, signal and dashboard configurations

Solution Scope

  • Machine structure and asset management
  • Electronic maintenance logbook and work orders
  • Live machine signals and SCADA dashboards
  • Alarm rules, notifications and incident workflow

Delivery Focus

We built an application that structures daily maintenance work and connects it with machine data. Operators can report issues, technicians can manage work orders and inspections, and leaders can track alarms, statuses and KPIs on dashboards.

Next.jsReactTailwind CSSFramer MotionNestJSPostgreSQL

Delivery Narrative

Challenge

Maintenance teams often work across spreadsheets, chat, paper documentation and separate machine panels. Alarms get lost, work history is fragmented and decisions are made without full operational context.

Solution

We built an application that structures daily maintenance work and connects it with machine data. Operators can report issues, technicians can manage work orders and inspections, and leaders can track alarms, statuses and KPIs on dashboards.

Outcome

The result is one place for requests, work orders, documentation, alarms and operational data. goConnecto can start as a maintenance system and grow into connected machine monitoring and SCADA dashboards.

Delivery Highlights

01

Maintenance CMMS

02

Machine monitoring and alarms

03

SCADA dashboards

Key Features

01

Machine structure and asset management

02

Electronic maintenance logbook and work orders

03

Live machine signals and SCADA dashboards

04

Alarm rules, notifications and incident workflow

05

Machine documentation and reporting

06

SEO-ready marketing website powered by Payload CMS

Impact Metrics

24/7

machine state and alarm visibility

1

shared maintenance timeline

∞

machine, signal and dashboard configurations

Next Step

Planning a Similar Platform or Workflow?

We can help you define delivery scope, architecture options, and implementation milestones.